Bridge Demolition, Manchester
Hardcore Crushing Ltd were delighted to be chosen by Eric Wright Civil Engineering to help undertake the complex bridge removal and demolition and dismantling works at Hyde, Manchester. This historic structure required specialist expertise and a carefully planned approach to ensure safe and controlled removal.
The Challenge
Bridge demolition presents unique structural and operational challenges. The structure at Hyde had to be carefully assessed prior to any dismantling works, with detailed method statements and structural engineering input to determine the correct sequence of operations. Working in proximity to roads, utilities and the public required strict access controls and methodical execution throughout.
The Approach
Our specialist demolition team and plant fleet were deployed to dismantle the structure section by section — controlling the works carefully to prevent unintended movement or collapse. All arising materials were segregated and processed for recycling, with steelwork removed and sent to local metal recyclers.
- Detailed structural assessment prior to works commencing
- Section-by-section controlled dismantling
- Traffic and public safety management throughout
- Steel structure recycled via local metal recyclers
- Masonry and concrete crushed and recycled on site
Chosen by Eric Wright Civil Engineering for our expertise in complex structural demolition — a vote of confidence in our team and our approach.
Result
The bridge structure was successfully removed, all materials disposed of correctly, and the site handed over clear and ready for the follow-on civil engineering works. Another specialist project delivered safely and on programme by Hardcore Crushing.
On Site

Complex. Controlled. Complete.
Chosen by Eric Wright Civil Engineering for our specialist expertise — bridge removed section by section with zero incidents and all materials recycled.
Related Projects

Grimsargh Skew Bridge, Lancashire
Footbridge demolition and enabling works for the Lancashire County Council road widening scheme at Grimsargh.
View Project
Airport Demolition Project
High-profile airport demolition — asbestos removal, soft strip, structural demolition and on-site crushing. 99% recycled.
View Project
The Christie Hospital, Manchester
Specialist works at a live hospital site — tight programme, vibration-sensitive environment, delivered on time and to a very high standard.
View ProjectNeed Emergency Demolition?
Available 24 hours a day, 7 days a week, 365 days a year across Lancashire and the North West.
Hardcore Crushing Ltd were delighted to be chosen by Eric Wright Civil Engineering to help undertake the complex bridge removal and demolition / dismantling works at Hyde, Manchester.
The historic disused railway bridge spanned the busy A57 Hyde Road and created a ‘bottle – neck’ reducing a 300m stretch of the road from four lanes to two; restricting traffic flow significantly at peak times.
The plan was to undertake a ‘military- style’ operation during extremely short timescale; closing the road over the weekend and then assembling one of the largest mobile cranes in the UK to lift the bridge from its current position.
The initial plan was to protect the carriageway surface and lift the bridge into the road and then dismantle over
a nightshift and get the road back open, but this was cancelled due to high winds and so an alternative approach was developed to lift the bridge deck down onto a portion of waste ground adjacent to the carriageway
, where we then had a little more time and ‘breathing – space’ to dismantle the steel structure into manageable pieces and removed all the materials from site.
The crane was assembled and set up on the Saturday and the bridge lifted down safely on
the Sunday and then we dismantled the whole 70 tonne structure and removed all materials from site, and we were off site by Tuesday.
The bridge was a mixture of composite steel beams; cross – bracing, and soffit decking, which was all riveted; welded, and generally bound together by 100 + years of compacted r ust, and as with all things of that era, it was built to last, so taking it apart required significant effort and the crushing power of a 35 tonne demolition specification hydraulic excavator equipped with specialist dismantling attachments for cutting and handling heavy metals.
Eric Wright Civil Engineering will then go on to create the road improvement works and install a new wider bridge to replace the link for cyclists and pedestrians.
We are pleased to report that the demolition works were carried out on programme and under budget.